Charlotte data center maintenance Maintenance Notification | 10/08/08
DATE: 10/08/2008
START TIME: 10/08/2008 22:00 EST
ESTIMATED COMPLETION TIME: 10/08/2008 23:00 EST
DURATION: 15 Minutes
SERVICES/EQUIPMENT: Authoritative DNS Servers
TYPE OF WORK: Hardware Change
PURPOSE OF WORK: Load Balancer Upgrade
LOCATION OF WORK: Charlotte
IMPACT OF WORK: Brief Outage
Charlotte data center will be performing hardware upgrades to its load balancers responsible for servicing queries to its authoritative DNS cluster.
We understand DNS services are a critical piece of infrastructure and will ensure the shortest interruption possible during the upgrade.
Charlotte data center acknowledges that typical upgrades should be hitless - however due to redundancy protocol incompatibility hitless upgrades will not be possible during this maintenance window.
Network Operations Center
Ahosting Managed HostingMatt